ExamPlay Light Logo
وارد شوید

Mathematics for IGCSE & O level - Proportion (Section 2 - No. 27)

The number of bricks needed to build a wall is inversely proportional to the number of workers. If it takes 8 workers 10 days to build a wall, how many days will it take 4 workers to build a wall?
5 days
10 days
16 days
20 days

توضیح

Days = k/workers; 10=k/8; k=80; Therefore, days = 80/4 = 20 days

نظرات (0)

ورود به نظر
تبلیغات
BrainBehindX Inc Logo
©2026; پشتیبانی شده توسط BrainBehindX Inc